N.M. Stat. § 62-18-5

Financing order; issuance; terms of bonds; reports to

N.M. Stat. § 62-18-5 · Last amended 2019 · Text from the 2026.09.1 snapshot

Text of § 62-18-5

commission of disbursement of bond proceeds; review and audit of

records.

A. The commission may approve an application for a financing order without a

formal hearing if no protest establishing good cause for a formal hearing is filed within

thirty days of the date when notice is given of the filing of the application for the

financing order. If a hearing is held, the commission shall issue an order granting or

denying the application for the financing order to a qualifying utility that is abandoning a

qualifying generating facility and an order on an accompanying application of the

qualifying utility for approval to abandon the qualifying generating facility within six

months from the date the application for the financing order is filed with the commission.

For good cause shown, the commission may extend the time for issuing the order for an

additional three months.

B. Failure to issue an order approving the application or advising of the application's

noncompliance pursuant to Subsection E of this section within the time prescribed by

Subsection A of this section shall be deemed approval of the application for a financing

order and approval to abandon the qualifying generating facility, if abandonment

approval was requested as part of the application for the financing order pursuant to this

subsection. The commission shall issue an order acknowledging the deemed approvals

within seven days of the expiration of the time period described in Subsection A of this

section.

C. If an application for a financing order is accompanied by a request for approval of

new resources, this section provides an alternative time frame to that provided in

Subsection C of Section 62-9-1 NMSA 1978, and the time frame specified in this section

shall govern, unless the request has been deferred to a separate proceeding pursuant

to Subsection D of Section 4 [62-18-4 NMSA 1978] of the Energy Transition Act.

D. The issuance of a financing order shall be the only approval required for the

authority granted in the financing order.

E. The commission shall issue a financing order approving the application if the

commission finds that the qualifying utility's application for the financing order complies

with the requirements of Section 4 of the Energy Transition Act. If the commission finds

that a qualifying utility's application does not comply with Section 4 of the Energy

Transition Act, the commission shall advise the qualifying utility of any changes

necessary to comply with that section and provide the applicant an opportunity to

amend the application to make such changes. Upon those changes being made, the

commission shall issue a financing order approving the application.

F. A financing order shall include the following provisions:

(1)

approval for the qualifying utility or assignee to issue energy transition

bonds as requested in the application, to use energy transition bonds to finance the

maximum amount of the energy transition costs as requested in the application, as may

be adjusted pursuant to Paragraph (6) of Subsection B of Section 4 of the Energy

Transition Act, and to use the proceeds provided in Subsection A of Section 10 [62-18-

10 NMSA 1978] of the Energy Transition Act;

(2)

approval for the qualifying utility to recover the energy transition costs, as

may be adjusted pursuant to Paragraph (6) of Subsection B of Section 4 of the Energy

Transition Act, requested in the application through energy transition charges;

(3)

approval of the energy transition charges necessary to recover the

authorized energy transition costs, to be imposed through a non-bypassable energy

transition charge as a separate line item on the qualifying utility's customer bills,

assessed consistent with energy and demand cost allocations within each customer

class, subject to update pursuant to the notice filing contemplated by Paragraph (6) of

Subsection B of Section 4 of the Energy Transition Act and subject to the application of

the adjustment mechanism as provided in Section 6 [62-18-6 NMSA 1978] of the

Energy Transition Act, until the energy transition bonds issued pursuant to the financing

order and the financing costs related to those bonds are paid in full;

(4)

approval of the adjustment mechanism in compliance with Section 6 of the

Energy Transition Act;

(5)

a description of the energy transition property that is created by the

financing order that may be used to pay, and secure the payment of, the energy

transition bonds and financing costs authorized to be issued in the financing order;

(6)

approval to enter into necessary or appropriate ancillary agreements;

(7)

approval of any plans for selling, assigning, transferring or conveying,

other than as a security, an interest in energy transition property; and

(8)

approval of the proposed ratemaking process and method included in the

application pursuant to Paragraphs (10) and (11) of Subsection B of Section 4 of the

Energy Transition Act.

G. A financing order shall provide that the creation of energy transition property shall

be simultaneous with the sale of the energy transition property to an assignee as

provided in the application and the pledge of the energy transition property to secure

energy transition bonds.

H. A financing order shall authorize the qualifying utility to issue one or more series

of energy transition bonds for a scheduled final maturity of no more than twenty-five

years for each series; provided that a rated final maturity may exceed twenty-five years.

With such authorization, the qualifying utility shall not subsequently be required to

secure a separate financing order prior to each issuance.

I. The commission may require, as a condition of the financing order and in every

circumstance subject to the limitations set forth in Subsection A of Section 7 [62-18-7

NMSA 1978] of the Energy Transition Act, that, during any period in which energy

transition bonds issued pursuant to the financing order are outstanding, an assignee

that is a non-utility affiliate and issues energy transition bonds shall provide in the

affiliate's articles of incorporation, partnership agreement or operating agreement, as

applicable, that in order for a person to file a voluntary bankruptcy petition on behalf of

that assignee, the prior unanimous consent of the directors, partners, managers or

members, as applicable, shall be required. Any such provision shall constitute a legal,

valid and binding agreement of such shareholders, partners or members of the

assignee and is enforceable against such shareholders, partners or members.

J. A financing order may require the qualifying utility to file with the commission a

periodic report showing the receipt and disbursement of proceeds of energy transition

bonds and any other documents necessary for the qualifying utility to implement the

financing order. Upon issuance of the energy transition bonds, the qualifying utility shall

file an advice notice with the commission, subject to review by the commission for errors

and corrections, that identifies the actual energy transition charges to be included on

customers' bills, effective fifteen days from the date the advice notice is filed.

K. A financing order may authorize the commission to review and audit the books

and records of the qualifying utility and of an assignee that is a non-utility affiliate and

issues energy transition bonds, relating to energy transition property and the receipt and

disbursement of proceeds of energy transition bonds.

L. After review and approval by the department of finance and administration with

regard to reasonableness of contracts for services, a financing order may authorize the

commission to impose a fee on the qualifying utility to pay commission expenses for

contract bond counsel accredited by a nationally recognized association of bond

lawyers to provide advice and assistance to commission staff in reviewing an

application for a financing order and the structure and marketing of the proposed energy

transition bonds.

M. The provisions of this section shall not be construed to limit the authority of the

commission to:

(1)

investigate the practices of or to audit the books and records of a

qualifying utility; or

(2)

issue such further orders as may be necessary to effectuate the provisions

of the Energy Transition Act.