LawCensus
New Mexico Statutes

N.M. Stat. § 62-18-4

Financing order; application contents; pending

N.M. Stat. § 62-18-4 · Last amended 2019 · Text from the 2026.09.1 snapshot

Text of § 62-18-4

applications.

A. A qualifying utility that is abandoning a qualifying generating facility may apply to

the commission for a financing order pursuant to this section to recover all of its energy

transition costs through the issuance of energy transition bonds. To obtain a financing

order, a qualifying utility shall obtain approval to abandon a qualifying generating facility

pursuant to Section 62-9-5 NMSA 1978. The application for the financing order may be

filed as part of the application for approval to abandon a qualifying generating facility.

B. An application for a financing order shall include:

(1)

a description of the facility that the qualifying utility proposes to abandon

or for which abandonment authority was granted after December 31, 2018;

(2)

an estimate of the energy transition costs and shall:

(a) identify the severance pay and job training expenses for affected

employees losing their jobs as a result of an abandoned qualifying generating facility

and any associated mine that only services the abandoned qualifying generating facility;

(b) identify costs not previously collected from the qualifying utility's

customers for plant decommissioning and mine reclamation costs, subject to any

limitations ordered by the commission prior to January 1, 2019 and affirmed by the New

Mexico supreme court prior to the effective date of the Energy Transition Act,

associated with the abandoned qualifying generating facility; and

(c) include an estimate of the financing costs associated with each series of

energy transition bonds proposed to be issued;

(3)

an estimate of the amount of energy transition charges necessary to

recover the costs in Paragraph (2) of this subsection and the proposed calculation

thereof, based on the estimated date of issuance and estimated principal amount of

each series of energy transition bonds proposed to be issued;

(4)

a description of the proposed adjustment mechanism that complies with

the provisions of Section 6 [62-18-6 NMSA 1978] of the Energy Transition Act;

(5)

a memorandum with supporting exhibits from a securities firm, such firm to

be attested to by the state board of finance as being experienced in the marketing of

bonds and capable of providing such a memorandum, that the proposed issuance

satisfies the current published AAA rating or equivalent rating criteria of at least one

nationally recognized statistical rating organization for issuances similar to the proposed

energy transition bonds. The request for such attestation may be made by a qualifying

utility prior to an application for a financing order, and the state board of finance shall

act upon such a request promptly;

(6)

a commitment by the qualifying utility to file with the commission following

the issuance of the energy transition bonds:

(a) a description of the final structure and pricing of the bonds;

(b) updated financing costs and payment amount required pursuant to

Section 16 [62-18-16 NMSA 1978] of the Energy Transition Act; and

(c) an updated calculation of the energy transition charges;

(7)

an estimate of timing of the issuance and term of the energy transition

bonds, or series of bonds; provided that the scheduled final maturity for each bond

issuance shall be no longer than twenty-five years;

(8)

identification of plans to sell, assign, transfer or convey, other than as a

security, interest in energy transition property, including identification of an assignee,

and demonstration that the assignee will be a financing entity wholly owned, directly or

indirectly, by the qualifying utility that will be initially capitalized by the qualifying utility in

such a way that equity interests in the financing entity are at least one-half percent of

the total capital of the assignee;

(9)

identification of ancillary agreements that may be necessary or

appropriate;

(10)

a description of a proposed ratemaking process to reconcile and recover

or refund any difference between the energy transition costs financed by the energy

transition bonds and the actual final energy transition costs incurred by the qualifying

utility or the assignee;

(11)

a proposed ratemaking method to account for the reduction in the

qualifying utility's cost of service associated with the amount of undepreciated

investments being recovered by the energy transition charge at the time that charge

becomes effective; and

(12)

a statement from the qualifying utility committing that the qualifying utility

will use commercially reasonable efforts to obtain the lowest cost objective.

C. The application may include requests for approvals for new resources

necessitated by the abandonment of a qualifying generating facility.

D. The qualifying utility or the commission may defer applications for needed

approvals for new resources to a separate proceeding; provided that the application

identifies adequate potential new resources sufficient to provide reasonable and proper

service to retail customers.

E. If an application for approval to abandon a qualifying generating facility is

pending before the commission on the effective date of the Energy Transition Act, the

qualifying utility may file a separate application for a financing order, and the

commission may join or consolidate the application for a financing order with the

pending proceeding involving abandonment of the qualifying generating facility, with the

consent of the applicant. On such joinder or consolidation, the time periods prescribed

by the Energy Transition Act shall become applicable to the joined or consolidated case

as of the date of the joinder or consolidation.

F. If a qualifying utility does not recover energy transition costs pursuant to the

Energy Transition Act, the energy transition costs may be recovered pursuant to other

applicable provisions of the Public Utility Act [Chapter 62, Articles 1 to 6 and 8 to 13

NMSA 1978].