N.M. Stat. § 13-1-122.4
Construction manager general contractor; multi-phased
Text of § 13-1-122.4
procedure.
A. The selection procedure shall use a competitive sealed qualifications-based
proposal method that conforms with Sections 13-1-111 through 13-1-117 NMSA 1978
and results in a professional services contract. The contract scope of work shall be
divided into two separate but related phases:
(1)
phase one for design consultation and preconstruction services; and
(2)
phase two for project construction.
B. The department shall issue a separate request for proposals for each project that
uses a construction manager general contractor delivery method.
C. The department's request for proposals for a construction manager general
contractor contract shall contain, at a minimum, the following elements:
(1)
a statement of the minimum qualifications for the construction manager
general contractor, including requirements for:
(a) a contractor's license for the type of work to be performed, issued
pursuant to the Construction Industries Licensing Act [Chapter 60, Article 13 NMSA
1978];
(b) registration pursuant to Section 13-4-13.1 NMSA 1978;
(c) minimum bond capacity;
(d) the ability to self-perform, with its own organization, a minimum
percentage of construction work as required and defined in the department's standard
specifications for highway and bridge construction, current edition; and
(e) current registration as a prequalified contractor pursuant to rule
promulgated by the department;
(2)
the procedures for submitting proposals, the criteria for evaluation of
qualifications and the relative weight of the criteria;
(3)
the form of contract to be awarded;
(4)
a listing or description of the types of preconstruction and construction
services that will be required;
(5)
identification of requirements for liability insurance, a proposal bond
pursuant to Section 13-1-146 NMSA 1978 and performance and payment bonds
pursuant to Section 13-4-18 NMSA 1978;
(6)
a description of the method to be used for pricing or negotiation of
construction manager general contractor fees for the scope of services; and
(7)
preferences as allowed by law in the Procurement Code for New-Mexico-
based businesses and others.
D. The department shall use a selection committee for the evaluation of the
qualifications submitted by offerors and shall determine the offerors that qualify for
award of the construction manager general contractor contract. The department shall
establish a construction manager general contractor selection committee by rule. The
selection committee shall rank the offerors and provide a recommendation to the
department identifying the offeror most qualified based on the highest ranking score.
E. Nothing in this section precludes the selection committee from recommending
the termination of the selection procedure pursuant to Section 13-1-131 NMSA 1978.
F. The department shall promulgate rules for the selection process and award of
contract that include interviews with top-ranked offerors, price negotiations and the
authority to terminate negotiations.
G. The department rules shall address the processes applicable to the award of a
contract for construction management and construction services, including the process
for conducting contract negotiations with the construction manager general contractor
for construction of the project or work packages associated with the project in
accordance with contract documents and specifications.
H. The department shall secure and use an independent cost estimate for the
project or each work package associated with the project to validate the negotiated
costs for the construction management and construction services contract. The
independent cost estimate shall remain confidential until notice of award of the
construction contract.
I. The construction manager general contractor shall submit a guaranteed
maximum price proposal for construction management and construction services for the
project or work packages associated with the project.
J. Negotiations may begin between the department and the construction manager
general contractor for the construction services before completion of the design work.
Upon successful negotiation, the department shall execute the contract with the
construction manager general contractor for construction of the project or work
packages associated with the project.
K. Negotiations shall be terminated if the department is unable to reach a price
agreement with the construction manager general contractor. In the event that
negotiations are terminated, the department may competitively bid the construction
phase of the project, in accordance with the department's procedures applicable to
public works construction projects. The construction manager general contractor may
be allowed to bid or provide subcontract services for the project, unless prohibited by
Section 10-16-13 NMSA 1978.
L. Data developed during the design services and the construction manager
general contractor's preconstruction services, unless otherwise protected by law, shall
be made available to all bidders.
M. After a construction manager general contractor contract is awarded for the
preconstruction services, the department shall make the names of each offeror and the
ranking and evaluation scores for each available for public inspection.
Cite this section
N.M. Stat. § 13-1-122.4
https://lawconsensus.com/codes/new-mexico/chapter-13/13-1-122-4/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.