Chapter 6. Power Facility and Site Certification
California Public Resources Code, § 25500 to § 25543. 72 sections.
- § 25500In accordance with the provisions of this division, the commission shall have the exclusive power to certify all sites and related facilities in the state, whether a new site and related facility or a change or addition …
- § 25500.1(a) The owner of a proposed solar thermal powerplant, for which an application for certification was filed with the commission after August 15, 2007, and certified by the commission and, of a project on federal land, for…
- § 25500.5The commission shall certify sufficient sites and related facilities which are required to provide a supply of electric power sufficient to accomodate the demand projected in the most recent forecast of statewide and ser…
- § 25501This chapter does not apply to any site or related facility for which the Public Utilities Commission has issued a certificate of public convenience and necessity or which any municipal utility has approved before Januar…
- § 25501.7Any person proposing to construct a facility or a site to which Section 25501 applies may waive the exclusion of such site and related facility from the provisions of this chapter by submitting to the commission a notice…
- § 25502Each person proposing to construct a thermal powerplant or electric transmission line on a site shall submit to the commission a notice of intention to file an application for the certification of the site and related fa…
- § 25502.3Except as provided in Section 25501.7, any person proposing to construct a facility excluded from the provisions of this chapter may waive such exclusion by submitting to the commission a notice of intention to file an a…
- § 25503Each notice of intention to file an application shall contain at least three alternative sites and related facilities, at least one of which shall not be located in whole or in part in the coastal zone. In addition, the …
- § 25504The notice of intention shall include a statement by the applicant describing the location of the proposed sites by section or sections, range and township, and county; a summary of the proposed design criteria of the fa…
- § 25504.5An applicant may, in the notice, propose a site to be approved which will accomodate a potential maximum electric generating capacity in excess of the capacity being proposed for the initial approval of the commission. I…
- § 25505Upon receipt of a notice, the commission shall cause a summary of the notice to be published in a newspaper of general circulation in each county in which the sites and related facilities, or any part thereof, designated…
- § 25506The commission shall request the appropriate local, regional, state, and federal agencies to make comments and recommendations regarding the design, operation, and location of the facilities designated in the notice, in …
- § 25506.5The commission shall request the Public Utilities Commission, for sites and related facilities requiring a certificate of public convenience and necessity, to make comments and recommendations regarding the design, opera…
- § 25507(a) If any alternative site and related facility proposed in the notice is proposed to be located, in whole or in part, within the coastal zone, the commission shall transmit a copy of the notice to the California Coasta…
- § 25508The commission shall cooperate with, and render advice to, the California Coastal Commission and the San Francisco Bay Conservation and Development Commission in studying applications for any site and related facility pr…
- § 25509Within 45 days of the filing of the notice, the commission shall conduct public informational presentations in the county or counties in which the proposed sites and related facilities are located. The place of such publ…
- § 25509.5No sooner than 15 days after the conclusion of the presentations pursuant to Section 25509, the commission shall commence nonadjudicatory hearings. Such hearings shall identify issues for adjudication in hearings pursuan…
- § 25510After the conclusion of such hearings, and no later than 150 days after filing of the notice, the commission shall prepare and make public a summary and hearing order on the notice of intention to file an application. Th…
- § 25511The commission shall review the factors related to safety and reliability of the facilities at each of the alternative sites designated in the notice. In addition to other information requested of the applicant, the comm…
- § 25512The summary and hearing order shall be based upon the record of the proceeding including statements or documents presented during any hearing or informational presentation on the notice, the comments transmitted by the P…
- § 25512.5Within 15 days of the publication of the summary and hearing order, a copy will be distributed to any person who requests such copy.
- § 25513No earlier than 30 days after distribution of the summary and hearing order, the commission shall commence adjudicatory hearings pursuant to the hearing order.
- § 25513.3Notwithstanding Sections 11425.30 and 11430.10 of the Government Code, unless a party demonstrates other statutory grounds for disqualification, a person who has served as investigator or advocate in an adjudicative proc…
- § 25514After conclusion of the hearings held pursuant to Section 25513 and no later than 300 days after the filing of the notice, a final report shall be prepared and distributed. The final report shall include, but not be limi…
- § 25514.3In specifying any modifications, conditions, or criteria pursuant to Section 25514, for sites and related facilities requiring a certificate of public convenience and necessity, the commission shall request the comments …
- § 25514.5In considering the acceptability of a site proposed to accommodate ultimately additional power-generating capacity, the commission, in determining, pursuant to Sections 25514 and 25512, the conformity of the facilities p…
- § 25515No later than 30 days after the final report is distributed, a hearing or hearings on the final report shall be commenced. Such hearings shall be concluded within 15 days of their commencement.
- § 25516The approval of the notice by the commission shall be based upon findings pursuant to Section 25514. The notice shall not be approved unless the commission finds at least two alternative site and related facility proposa…
- § 25516.1If a site and related facility found to be acceptable by the commission pursuant to Section 25516 is located in the coastal zone, the Suisun Marsh, or the jurisdiction of the San Francisco Bay Conservation and Developmen…
- § 25516.5On a notice which proposes an expanded ultimate electric generating capacity for a site, the commission may, based upon findings pursuant to Section 25514, either approve the notice only for the initial facility or facil…
- § 25516.6(a) Except as otherwise expressly provided in this division, the commission shall issue its written decision on the notice not later than 12 months after the notice is filed, or at any later time as is mutually agreed up…
- § 25517Except as provided in Section 25501, no construction of any thermal powerplant or electric transmission line shall be commenced by any electric utility without first obtaining certification as prescribed in this division…
- § 25518The Public Utilities Commission shall issue no certificate of public convenience and necessity for a site or related electrical facilities unless the utility has obtained a certificate from the commission.
- § 25518.5Nothing in this division shall preclude the concurrent initiation of an application for a certificate of public convenience and necessity from the Public Utilities Commission subject to the condition specified in Section…
- § 25519(a) To obtain certification for a site and related facility, an application for certification of the site and related facility shall be filed with the commission. The application shall be in a form prescribed by the comm…
- § 25519.5(a) If the site and related facilities specified in the application are proposed to be located within 1,000 feet of a military installation, or lie within special use airspace or beneath a low-level flight path, as defin…
- § 25520The application shall contain all of the following information and any other information that the commission by regulation may require: (a) A detailed description of the design, construction, and operation of the propos…
- § 25520.5(a) In reviewing an application for an additional facility at a potential multiple-facility site, the commission shall undertake a reconsideration of its prior determinations in the final report on the notice for the sit…
- § 25521No earlier than 90 nor later than 240 days after the date of the filing of an application, the commission shall commence a public hearing or hearings on the application in Sacramento, San Francisco, Los Angeles, or San D…
- § 25522(a) Except as provided in subdivision (c) of Section 25520.5, within 18 months of the filing of an application for certification, or within 12 months if it is filed within one year of the commission’s approval of the not…
- § 25523The commission shall prepare a written decision after the public hearing on an application, which includes all of the following: (a) Specific provisions relating to the manner in which the proposed facility is to be des…
- § 25524(a) “Qualified applicant” for purposes of this section means an applicant for certification of an eligible renewable energy resource, as defined in the California Renewables Portfolio Standard Program (Article 16 (commen…
- § 25524.1(a) Except for the existing Diablo Canyon Units 1 and 2 owned by Pacific Gas and Electric Company and San Onofre Units 2 and 3 owned by Southern California Edison Company and San Diego Gas and Electric Company, no nuclea…
- § 25524.2Except for the existing Diablo Canyon Units 1 and 2 owned by Pacific Gas and Electric Company and San Onofre Units 2 and 3 owned by Southern California Edison Company and San Diego Gas and Electric Company, no nuclear fi…
- § 25524.5The commission shall not certify any facility which adds generating capacity to a potential multiple-facility site in excess of the maximum allowable capacity established by the commission pursuant to Section 25516.5, un…
- § 25525The commission may not certify a facility contained in the application when it finds, pursuant to subdivision (d) of Section 25523, that the facility does not conform with any applicable state, local, or regional standar…
- § 25526(a) The commission shall not approve as a site for a facility any location designated by the California Coastal Commission pursuant to subdivision (b) of Section 30413, unless the California Coastal Commission first find…
- § 25527The following areas of the state shall not be approved as a site for a facility, unless the commission finds that such use is not inconsistent with the primary uses of such lands and that there will be no substantial adv…
- § 25528(a) The commission shall require, as a condition of certification of any site and related facility, that the applicant acquire, by grant or contract, the right to prohibit development of privately owned lands in the area…
- § 25529When a facility is proposed to be located in the coastal zone or any other area with recreational, scenic, or historic value, the commission shall require, as a condition of certification of any facility contained in the…
- § 25530The commission may order a reconsideration of all or part of a decision or order on its own motion or on petition of any party. Any such petition shall be filed within 30 days after adoption by the commission of a decis…
- § 25531(a) The decisions of the commission on any application for certification of a site and related facility are subject to judicial review by the Supreme Court of California. (b) No new or additional evidence may be introdu…
- § 25532The commission shall establish a monitoring system to assure that any facility certified under this division is constructed and is operating in compliance with air and water quality, public health and safety, and other a…
- § 25534(a) The commission may, after one or more hearings, amend the conditions of, or revoke the certification for, any facility for any of the following reasons: (1) Any material false statement set forth in the application,…
- § 25534.1(a) The executive director of the commission may issue a complaint to any person or entity on whom an administrative civil penalty may be imposed pursuant to Section 25534. The complaint shall allege the act or failure t…
- § 25534.2(a) Within 30 days after service of an order issued under Section 25534.1, any aggrieved party may file with the superior court a petition for writ of mandate for review thereof pursuant to Section 1094.5 of the Code of …
- § 25535Such reasonable and direct costs as the applicant incurs to comply with the provisions of this chapter shall be allowed for ratemaking purposes.
- § 25537Upon approval of an application, the commission shall forward to the United States Nuclear Regulatory Commission, the Environmental Protection Agency, and to other appropriate federal agencies, the results of its studies…
- § 25538Upon receiving the commission’s request for review under subdivision (f) of Section 25519 and Section 25506, the local agency may request a fee from the commission to reimburse the local agency for the actual and added c…
- § 25539In reviewing notices and applications for certification of modifications of existing facilities, the commission shall adopt rules and regulations as necessary to insure that relevant duties pursuant to this division are …
- § 25540If a person proposes to construct a geothermal powerplant and related facility or facilities on a site, the commission shall not require three alternative sites and related facilities to be proposed in the notice. Except…
- § 25540.1The commission shall determine, within 30 days after the receipt of a notice or application for a geothermal powerplant, whether the notice or application is complete. If the notice or application is determined not to be…
- § 25540.2Notwithstanding any other provision of law: (a) If an applicant proposes to construct a geothermal powerplant at a site which, at the outset of the proceeding, the applicant can reasonably demonstrate to be capable of p…
- § 25540.3(a) An applicant for a geothermal powerplant may propose a site to be approved that will accommodate a potential maximum electric generating capacity in excess of the capacity being proposed for initial construction. In …
- § 25540.4Notwithstanding any other provision of law: (a) The decision of the commission on an application for an additional facility at a potential multiple facility site shall be issued within three months after the acceptance …
- § 25540.5The commission may, at the petition of a county which has adopted a geothermal element for its general plan, approve an equivalent certification program which delegates to that county full authority for the certification…
- § 25540.6(a) Notwithstanding any other provision of law, no notice of intention is required, and the commission shall issue its final decision on the application, as specified in Section 25523, within 12 months after the filing o…
- § 25541The commission may exempt from this chapter thermal powerplants with a generating capacity of up to 100 megawatts and modifications to existing generating facilities that do not add capacity in excess of 100 megawatts, i…
- § 25541.1It is the intent of the Legislature to encourage the development of thermal powerplants using resource recovery (waste-to-energy) technology. Previously enacted incentives for the production of electrical energy from non…
- § 25541.5(a) On or before January 1, 2001, the Secretary of the Resources Agency shall review the regulatory program conducted pursuant to this chapter that was certified pursuant to subdivision (k) of Section 15251 of Title 14 o…
- § 25542In the case of any site and related facility or facilities for which the provisions of this division do not apply, the exclusive power given to the commission pursuant to Section 25500 to certify sites and related facili…
- § 25543(a) It is the intent of the Legislature to improve the process of siting and licensing new thermal electric powerplants to ensure that these facilities can be sited in a timely manner, while protecting environmental qual…