(a) The planning commission is vested with all the necessary authority to administer and enforce conditions attached to the final plat approved for a development project, including, but not limited to, the authority to:

(1) Order, in writing, the remedy for any noncompliance with the conditions;

(2) Bring legal action to ensure compliance with the conditions, including injunction, abatement, or other appropriate action or proceeding; and

(3) Require a guarantee satisfactory to the planning commission in an amount sufficient for and conditioned upon the construction of any physical improvements required by the conditions, or a contract for the construction of the improvements and the contractor's guarantee, in like amount and so conditioned, which guarantee shall be reduced or released by the planning commission upon the submission of satisfactory evidence that construction of the improvements has been completed in whole or in part.

(b) Failure to meet all conditions attached to the final plat approved for a development project shall constitute cause to deny the issuance of any of the required use, occupancy or improvement location permits, as may be appropriate.

Cite this section

W. Va. Code § 8A-6-3

https://lawconsensus.com/codes/west-virginia/chapter-8a/8a-6-3/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.