LawCensus
Revised Code of Washington

RCW 54.40.030

Transmittal of copies of federal hydroelectric license to county auditor

RCW 54.40.030 · Last amended 1977 · Text from the 2026.09.1 snapshot

Text of § 030

Within five days after a public utility district shall receive a license from the federal power commission to construct a hydroelectric project of an estimated cost of more than two hundred and fifty million dollars, including interest during construction, or, in the case of a district which on September 21, 1977, is in existence and has such a license within five days of September 21, 1977, the district shall forward a true copy of said license, certified by the secretary of the district, to the county auditor of the county wherein said district is located.

Cite this section

RCW 54.40.030

https://lawconsensus.com/codes/washington/title-54/54-40-030/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.