RCW 4.24.360
Construction contract provision waiving, releasing, etc., rights of contractor, etc., to damages or adjustment for unreasonable delay caused by contractee, etc.—Declared void and unenforceable—Exceptions
Text of § 360
Any clause in a construction contract, as defined in RCW 4.24.370 , which purports to waive, release, or extinguish the rights of a contractor, subcontractor, or supplier to damages or an equitable adjustment arising out of unreasonable delay in performance which delay is caused by the acts or omissions of the contractee or persons acting for the contractee is against public policy and is void and unenforceable. This section shall not be construed to void any provision in a construction contract, as defined in RCW 4.24.370 , which (1) requires notice of delays, (2) provides for arbitration or other procedure for settlement, or (3) provides for reasonable liquidated damages.
Cite this section
RCW 4.24.360
https://lawconsensus.com/codes/washington/title-4/4-24-360/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.