RCW 39.10.320
Design-build procedure—Project management and contracting requirements
Text of § 320
(1) A public body utilizing the design-build contracting procedure shall provide: (a) Reasonable budget contingencies totaling not less than five percent of the anticipated contract value; (b) Staff or consultants with expertise and prior experience in the management of comparable projects; (c) Contract documents that include alternative dispute resolution procedures to be attempted prior to the initiation of litigation; (d) Submission of project information, as required by the board; (e) Contract documents that require the contractor, subcontractors, and designers to submit project information required by the board; and (f) Contract documents that require the design builder to submit plans for inclusion of underutilized firms as subcontractors and suppliers including, but not limited to, the office of minority and women's business enterprises certified businesses, veteran certified businesses, and small businesses as allowed by law. (2) A public body utilizing the design-build contracting procedure may provide incentive payments to contractors for early completion, cost savings, or other goals if such payments are identified in the request for proposals.
Cite this section
RCW 39.10.320
https://lawconsensus.com/codes/washington/title-39/39-10-320/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.