RCW 36.70B.260
Electricity projects—Prohibition on demonstration of need
Text of § 260
During project review of a project to construct or improve facilities for the generation, transmission, or distribution of electricity, a local government may not require a project applicant to demonstrate the necessity or utility of the project other than to require, as part of a completed application under RCW 36.70B.070 (2), submission of any publicly available documentation required by the federal energy regulatory commission or its delegees or the utilities and transportation commission or its delegees, or from any other federal agency with regulatory authority over the assessment of electric power transmission and distribution needs as applicable.
Cite this section
RCW 36.70B.260
https://lawconsensus.com/codes/washington/title-36/36-70b-260/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.