Processor's form showing maximum processing capacity

RCW 20.01.510 · Last amended 2011 · Text from the 2026.09.1 snapshot

Text of § 510

In order to carry out the purposes of this chapter, the director may require a processor to annually complete a form prescribed by the director, which, when completed, will show the maximum processing capacity of each plant operated by the processor in the state of Washington. Such completed form shall be returned to the director by a date prescribed by him or her.

Cite this section

RCW 20.01.510

https://lawconsensus.com/codes/washington/title-20/20-01-510/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.