RELIABILITY PLAN FOR REGIONS WITH RAPID ELECTRICAL LOAD GROWTH

Tex. Utilities Code § 39.166 · Last amended 2023 · Text from the 2026.09.1 snapshot

Text of § 39.166

(a) The commission shall direct the independent organization certified under Section 39.151 for the ERCOT power region to:

(1) identify each region in which transmission capacity is insufficient to meet the region's existing and forecasted electrical load, as reasonably determined by the certificated transmission service provider; and

(2) develop a reliability plan to serve existing and forecasted electrical load in the identified region.

(b) The commission shall develop a plan to implement each reliability plan adopted under Subsection (a) to ensure timely development and approval of necessary transmission service improvements.