Tex. Utilities Code § 36.154
DEADLINE
Text of § 36.154
(a) The regulatory authority shall make a final determination not later than the 185th day after the date the electric utility files the rate-filing package required by Section 36.153.
(b) The deadline prescribed by Subsection (a) is extended two days for each day the actual hearing on the merits of the case exceeds 15 days.
Cite this section
Tex. Utilities Code § 36.154
https://lawconsensus.com/codes/texas/utilities-code/36-154/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.