Tex. Property Code § 53.103
LIEN ON RESERVED FUNDS
Text of § 53.103
A claimant has a lien on the reserved funds if the claimant:
(1) sends the notices required by this chapter in the time and manner required; and
(2) except as allowed by Section 53.057(f), files an affidavit claiming a lien not later than the 30th day after the earliest of the date:
(A) the work is completed;
(B) the original contract is terminated; or
(C) the original contractor abandons performance under the original contract.
Cite this section
Tex. Property Code § 53.103
https://lawconsensus.com/codes/texas/property-code/53-103/