Tex. Local Government Code § 284.153

GENERAL PROCESS RELATING TO PERMIT APPLICATION

Tex. Local Government Code § 284.153 · Last amended 2017 · Text from the 2026.09.1 snapshot

Text of § 284.153

(a) Except as otherwise provided by this section, a municipality may not require an applicant to provide more information to obtain the permit than a telecommunications utility that is not a network provider is required to provide unless the information directly relates to the requirements of this chapter.

(b) As part of the standard form for a permit application, a municipality may require the applicant to include applicable construction and engineering drawings and information to confirm that the applicant will comply with the municipality's publicly disclosed public right-of-way design specifications and applicable codes.

(c) A municipality may require an applicant to provide:

(1) information reasonably related to the provider's use of the public right-of-way under this chapter to ensure compliance with this chapter;

(2) a certificate that the network node complies with applicable regulations of the Federal Communications Commission; and

(3) certification that the proposed network node will be placed into active commercial service by or for a network provider not later than the 60th day after the date the construction and final testing of the network node is completed.

Cite this section

Tex. Local Government Code § 284.153

https://lawconsensus.com/codes/texas/local-government-code/284-153/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.