Tex. Government Code § 2253.046
NOTICE REQUIRED FOR CLAIM FOR PAYMENT OF RETAINAGE
Text of § 2253.046
(a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment of retainage, a payment bond beneficiary whose contract with a prime contractor or subcontractor provides for retainage must mail written notice of the claim to the prime contractor and the surety on or before the 90th day after the date of final completion of the public work contract.
(b) The notice shall consist of a statement of:
(1) the amount of the contract;
(2) any amount paid; and
(3) the outstanding balance.
(c) Notice of a claim for payment of retainage is not required if the amount claimed is part of a prior claim made under this subchapter.
Cite this section
Tex. Government Code § 2253.046
https://lawconsensus.com/codes/texas/government-code/2253-046/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.