Tex. Government Code § 2253.043

NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIAL WHEN WRITTEN AGREEMENT DOES NOT EXIST

Tex. Government Code § 2253.043 · Last amended 1993 · Text from the 2026.09.1 snapshot

Text of § 2253.043

(a) Except as provided by Section 2253.044, if a written agreement does not exist between the payment bond beneficiary and the prime contractor or between the payment bond beneficiary and the subcontractor, the notice for a claim for unpaid bills must contain:

(1) the name of the party for whom the public work labor was performed or to whom the public work material was delivered;

(2) the approximate date of performance or delivery;

(3) a description of the public work labor or material for reasonable identification; and

(4) the amount due.

(b) The payment bond beneficiary must generally itemize the claim and include with it copies of documents, invoices, or orders that reasonably identify:

(1) the public work labor performed or public work material delivered for which the claim is made;

(2) the job; and

(3) the destination of delivery.

Cite this section

Tex. Government Code § 2253.043

https://lawconsensus.com/codes/texas/government-code/2253-043/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.