62 Pa.C.S. § 3922
Payment of retainage to subcontractors
Text of § 3922
In the absence of sufficient reason, within 20 days of the receipt of payment by the contractor, the contractor shall pay all subcontractors with which it has contracted their earned share of the payment the contractor received. SUBCHAPTER D PROMPT PAYMENT SCHEDULES Sec. 3931. Performance by contractor or subcontractor. 3932. Government agency's progress payment obligations. 3933. Contractors' and subcontractors' payment obligations. 3934. Withholding of payment for good faith claims. 3935. Penalty and attorney fees. 3936. Contracts involving Federal aid. 3937. Certain provisions unenforceable. 3938. Applicability. 3939. Claims by innocent parties.
Cite this section
62 Pa.C.S. § 3922
https://lawconsensus.com/codes/pennsylvania/title-62/3922/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.