ORS 758.545
Electric utility required to make good faith effort to transmit energy; remedy
Text of § 758.545
758.545 Electric utility required to make good faith effort to transmit energy; remedy. (1) If an electric utility fails to make a good faith effort to comply with a request from a qualifying facility to transmit energy or energy and capacity produced by the qualifying facility to another electric utility or to the Bonneville Power Administration, the electric utility shall purchase the qualifying facility’s energy or energy and capacity at a price which is the higher of:
(a) The electric utility’s avoided cost; or
(b) The index rate.
(2) As used in this section, “good faith effort” shall be demonstrated by the electric utility’s publication of a generally applicable, reasonable policy of the electric utility to allow a qualifying facility to use the electric utility’s transmission facilities on a cost-related basis. [1983 c.799 §5]
Cite this section
ORS 758.545
https://lawconsensus.com/codes/oregon/title-57/758-545/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.