LawCensus
Oregon Revised Statutes

ORS 701.430

Performance bond; terms

ORS 701.430 · Last amended 2024 · Text from the 2026.09.1 snapshot

Text of § 701.430

701.430 Performance bond; terms. A contractor or subcontractor may execute and deliver to the owner, contractor or subcontractor before the commencement of construction for which the contractor or subcontractor will be responsible for performing a good and sufficient bond in a sum equal to the contract price for the faithful performance of the contract. The term of the bond obtained under this subsection must extend to include the period during which claims of lien or notices of other encumbrances based on the construction performed under the contract may be filed under applicable law. The bond must be approved by the owner, contractor or subcontractor entitled to withhold retainage. A faithful performance bond delivered under this section must include, but not be limited to, provisions to the effect that:

(1) The obligations of the contract must be faithfully performed;

(2) Payment must promptly be made to all persons supplying labor or materials to the contractor or subcontractor for prosecution of the work provided in the contract;

(3) All contributions due the Industrial Accident Fund and the Unemployment Compensation Trust Fund from the contractor or subcontractor in connection with the performance of the contract must be made promptly; and

(4) All sums required to be deducted and retained from the wages of employees of the contractor or subcontractor pursuant to the Personal Income Tax Act of 1969, must be paid over to the Department of Revenue. [1975 c.772 §3; 2013 c.410 §3; 2024 c.2 §3]

Note: See note under 701.410.

Cite this section

ORS 701.430

https://lawconsensus.com/codes/oregon/title-52/701-430/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.