ORS 543.265
Testing of fish protection measures as condition for hydroelectric project permit or license; scope and cost
Text of § 543.265
543.265 Testing of fish protection measures as condition for hydroelectric project permit or license; scope and cost. The Water Resources Department shall impose as a condition to any water right permit to appropriate water for hydroelectric purposes granted under ORS 537.211 or any license granted under ORS 543.260 that the person operating the hydroelectric project shall, during the operational lifetime of the project, perform or allow the State Department of Fish and Wildlife to perform, any tests or studies required by the department to evaluate the effectiveness of measures for the protection of fish. The scope and cost of these studies will be negotiated between the State Department of Fish and Wildlife and the operator. [1985 c.674 §6; 1987 c.158 §116; 1995 c.416 §40]
Note: 543.265 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 543 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.
Cite this section
ORS 543.265
https://lawconsensus.com/codes/oregon/title-45/543-265/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.