ORS 517.986
Time limit for final action on permit subject to consolidated application process
Text of § 517.986
517.986 Time limit for final action on permit subject to consolidated application process. Notwithstanding any other provision of law, the State Department of Geology and Mineral Industries and any other permitting agency shall take final action to issue or deny a permit subject to the consolidated application process set forth in ORS 517.952 to 517.989 within one year after issuance of a notice to proceed under ORS 517.977. However, with the concurrence of the applicant, the processing of the application may be suspended for a period of time to allow the applicant to resolve issues having a bearing on, or necessary to any permitting agency’s decision or the department’s decision on whether to issue or deny a permit. [1991 c.735 §24]
Cite this section
ORS 517.986
https://lawconsensus.com/codes/oregon/title-43/517-986/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.