ORS 517.981
Draft permit and permit conditions; denial of permit; time limits; public hearing on draft permit
Text of § 517.981
517.981 Draft permit and permit conditions; denial of permit; time limits; public hearing on draft permit. (1) Within 225 days after receiving the completed consolidated application and the environmental evaluation conducted under ORS 517.979, each permitting agency shall provide its draft permit and permit conditions or its denial document to the State Department of Geology and Mineral Industries. If a permitting agency includes in its draft permit a condition that is inconsistent with the environmental evaluation conducted pursuant to ORS 517.979, the agency shall include with its draft permit a written explanation of the condition setting forth the findings of the agency that support the condition. The State Department of Geology and Mineral Industries shall assure that the conditions imposed on the permits by the cooperating agencies do not conflict. If the department finds a conflict exists, the technical review team shall resolve the conflict.
(2) Within 15 days after receiving all draft permits and the completion of its draft operating permit, the State Department of Geology and Mineral Industries shall issue notice of an opportunity for public comment and a consolidated public hearing on all draft permits. The public hearing shall occur not sooner than 45 days after the department issues the notice. The notice shall be issued in accordance with ORS 517.959. [1991 c.735 §19]
Cite this section
ORS 517.981
https://lawconsensus.com/codes/oregon/title-43/517-981/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.