ORS 307.677
Extension of construction period; effect of destruction of property
Text of § 307.677
307.677 Extension of construction period; effect of destruction of property. Notwithstanding ORS 307.651 to 307.687:
(1) If the city finds that construction of single-unit housing was not completed in accordance with ORS 307.651 (4)(b), the city may extend the deadline for completion of construction for a period not to exceed an additional 24 consecutive months if the city further finds that:
(a) The failure to complete construction was due to circumstances beyond the control of the owner; and
(b) The owner had been acting and could reasonably be expected to act in good faith and with due diligence.
(2) If property granted exemption under ORS 307.651 to 307.687 is destroyed by fire or act of God, or is otherwise no longer capable of occupancy due to circumstances beyond the control of the owner, the exemption shall cease but no additional taxes or penalty shall be imposed under ORS 307.651 to 307.687 upon the property. [Formerly 458.065; 2017 c.294 §4; 2021 c.528 §10; 2024 c.52 §20]
Cite this section
ORS 307.677
https://lawconsensus.com/codes/oregon/title-29/307-677/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.