Text of § 279C.625

279C.625 Joint liability when payment bond not executed. If the public improvement contract is one for which a payment bond as provided for in ORS 279C.380 and 279C.400 is required and the contractor fails to pay for labor or materials or to pay claims due the Industrial Accident Fund, the Unemployment Compensation Trust Fund or the Department of Revenue and the officers of the public body that authorized the contract fail or neglect to require the person entering into the contract to execute the payment bond:

(1) The State of Oregon and the officers authorizing the contract shall be jointly liable for the labor and materials used in the performance of any work under the contract, and for claims due the Industrial Accident Fund, the Unemployment Compensation Trust Fund and the Department of Revenue, if the contract was entered into with the State of Oregon.

(2) The public body and the officers authorizing the contract shall be jointly liable for the labor and materials used in the performance of any work under the contract and for claims due the Industrial Accident Fund, the Unemployment Compensation Trust Fund and the Department of Revenue, if the contract was entered into on behalf of a public body other than the state. [2003 c.794 §159; 2005 c.103 §35]

Cite this section

ORS 279C.625

https://lawconsensus.com/codes/oregon/title-26/279c-625/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.