Time limit.
A. If a subcontractor or material supplier has performed in
accordance with the provisions of a construction contract, the prime
contractor shall make payment to the subcontractor or material
supplier no later than ten (10) calendar days after the prime
contractor receives its corresponding payment for the work
performed.
B. If a sub-subcontractor or material supplier has performed in
accordance with the provisions of a construction contract, the sub-
subcontractor or material supplier shall be entitled to receive
payment no later than seven (7) calendar days after subcontractor
receives its corresponding payment for the work performed.