Okla. Stat. tit. 40, § 40-175
Temporary floorings in steel frame buildings
Text of § 40-175
If in the erection of an iron or steel framed building, the
spaces between the girders or floor beams of any floor are not
filled or covered by the permanent construction of said floors
before another story is added to the building, a close plank
flooring shall be placed and maintained over such spaces, during the
construction of each story, from the time when the beams or girders
are placed in position; but openings protected by a strong hand
railing not less than four (4) feet high may be left through said
floors for the passage of workmen and material.
Cite this section
Okla. Stat. tit. 40, § 40-175
https://lawconsensus.com/codes/oklahoma/title-40/40-175/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.