Ohio Rev. Code § 5525.22
Demolition contracts
Text of § 5525.22
June 30, 1995 House Bill 107 - 121st General Assembly For contracts for projects that involve the demolition of property for a right-of-way, the director of transportation shall include in the contract adequate provision for liquidated damages and a requirement that the contractor inform the department of the method for disposal of demolition debris prior to the start of work.
Cite this section
Ohio Rev. Code § 5525.22
https://lawconsensus.com/codes/ohio/title-55/5525-22/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.