Ohio Rev. Code § 5525.10
Contracts not to be awarded for more than cost plus five per cent
Text of § 5525.10
June 29, 2005 House Bill 68 - 126th General Assembly Except as provided in section 5525.15 of the Revised Code, no contract for any road improvement shall be awarded for a greater sum than the estimated cost thereof plus five per cent. The bids received for an improvement shall be opened at the time and place stated in the notice and the bids shall conform to such other requirements as the director of transportation prescribes. If no acceptable bid is made the director may readvertise the work at the original estimate or amend the estimate and again proceed to advertise for bids. The director may contract for the construction or improvement of bridges and culverts or the grading required in connection with an improvement and may defer making contracts for the remainder of said improvement until such grade has become stable and solid.
Cite this section
Ohio Rev. Code § 5525.10
https://lawconsensus.com/codes/ohio/title-55/5525-10/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.