Text of § 4906.212

October 11, 2021 Senate Bill 52 - 134th General Assembly The estimate of the total decommissioning costs of a utility facility, as described in division (B)(3) of section 4906.211 of the Revised Code, shall be recalculated every five years by an engineer retained by the applicant.