N.M. Stat. § 72-5-6
Hearing; approval; permit
Text of § 72-5-6
Upon the receipt of the proofs of publication, accompanied by any statutory fees
required at this time, the state engineer shall determine, from the evidence presented by
the parties interested, from such surveys of the water supply as may be available and
from the records, whether there is unappropriated water available for the benefit of the
applicant. If so, and if the proposed appropriation is not contrary to the conservation of
water within the state and is not detrimental to the public welfare of the state, the state
engineer shall endorse his approval on the application, which shall become a permit to
appropriate water, and shall state in such approval the time within which the
construction shall be completed and the time within which water shall be applied to a
beneficial use; provided that the state engineer may, in his discretion, approve any
application for a less amount of water or may vary the periods of annual use, and the
permit to appropriate water shall be regarded as limited accordingly. The time allowed
by the state engineer for completion of works or application of water to beneficial use
shall be governed by the size and complexity of the project, but in no case shall exceed
five years from the date of approval within which to complete construction, and four
years in addition thereto within which to apply water to a beneficial use; provided that
the state engineer shall have the power to grant extensions of time for completion of
works or application of water to beneficial use as provided in Section 72-5-14 NMSA
1978.