N.M. Stat. § 72-5-14
Time for construction; extension
Text of § 72-5-14
The state engineer shall have the power to grant extensions of time in which to
complete construction of works, to apply water to beneficial use and for such other
reasonable purpose as may in his opinion appear, under any water right application on
file in his office, upon proper showing by the applicant of due diligence or reasonable
cause for delay. Extensions of time not exceeding five years beyond the time for
construction allowed in the original permit, and in no case exceeding a total of ten years
after the date of approval of the application, may be granted by the state engineer for
construction of works and application of water to beneficial use; provided, that if it shall
be made to appear to the state engineer by affidavit of the applicant, his successors or
assigns, or by any person for or on behalf of such applicant, and by such other evidence
as the state engineer may require, that at least one-fourth of the actual construction
work has been completed within such period as extended, the state engineer may, if he
is satisfied of the good faith of the applicant and that the project will be to the interest of
the development of the state, extend the time for completion of works and application of
water to beneficial use for any additional periods he may deem necessary, but not
exceeding two years for any one extension, upon such reasonable terms and conditions
as he may prescribe; and at the time of granting such extension shall endorse his
approval thereon and shall make the proper entry in his records.
Cite this section
N.M. Stat. § 72-5-14
https://lawconsensus.com/codes/new-mexico/chapter-72/72-5-14/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.