N.M. Stat. § 70-4-3
Liens of subcontractors
Text of § 70-4-3
Any person who furnishes or hauls the material, tools, equipment, machinery or
supplies as, or to, a subcontractor, or any person who performs the labor for, or under,
a subcontract with a contractor or subcontractor shall have a lien upon the whole of the
land, oil and gas permit, leasehold, lease for oil and gas purposes, or oil pipeline, gas
pipeline or gasoline pipeline, and the right-of-way therefor, buildings and equipment
thereon, and the appurtenances thereto, and upon the materials, tools, machinery,
equipment and supplies so furnished or hauled, and upon the oil and gas well for which
they were furnished or hauled, and upon all the other oil and gas wells, fixtures,
machinery, tools, equipment and appliances used in operating or developing for oil and
gas purposes upon the land, oil and gas permit, leasehold, or lease for oil and gas
purposes, for which the material, tools, machinery, equipment or supplies were
furnished or hauled, or labor performed, to the same extent, with the same preferences
and priorities, and on an equality with the lien of an original contractor as provided in
Sections 70-4-1 and 70-4-2 NMSA 1978, for the amount due him for the labor, hauling
or materials, tools, machinery, equipment or supplies.
Cite this section
N.M. Stat. § 70-4-3
https://lawconsensus.com/codes/new-mexico/chapter-70/70-4-3/