A. Crude oil severed and sold from an enhanced recovery project or the expansion

of an existing project shall qualify for the recovered oil tax rate if, before the enhanced

recovery project or expansion begins operation, the division approves the project or

expansion and designates the area to be affected by the project or expansion, but no

project or expansion approved by the division prior to the effective date of the Enhanced

Oil Recovery Act shall qualify for the recovered oil tax rate.

B. The operator of a proposed enhanced recovery project or expansion shall apply

to the division for approval of the proposed enhanced recovery project or expansion and

shall provide the division with any relevant information the division requires for that

approval.

C. If approval by the division of a unitization agreement as set forth in Chapter 70,

Article 7 NMSA 1978 is required for purposes of carrying out the enhanced recovery

project or expansion, the division shall not approve the enhanced recovery project or

expansion unless it approves the unitization agreement.

D. An operator may apply for approval of a proposed enhanced recovery project or

expansion concurrently with an application for approval of a unitization agreement as

set forth in Chapter 70, Article 7 NMSA 1978 for the purposes of carrying out the

proposed enhanced recovery project or expansion.

E. The division shall only approve a proposed enhanced recovery project or

expansion if it determines that the application for approval has not been prematurely

filed either for economic or technical reasons and that the area to be affected by the

enhanced recovery project or expansion has been so depleted that it is prudent to apply

enhanced recovery techniques to maximize the ultimate recovery of crude oil from the

well or pool.

F. Upon the approval of the application for an enhanced recovery project or

expansion, the division shall issue a certification of approval to the operator and

designate the area to be affected by the enhanced recovery project or expansion.

G. The recovered oil tax rate shall apply only to the crude oil produced from the area

the division certifies to be affected by the enhanced recovery project or expansion.

H. The operator shall file an application for certification of a positive production

response with the division to be eligible to receive the recovered oil tax rate.

I. The recovered oil tax rate shall only apply to crude oil produced from an

enhanced recovery project or the expansion of an existing project beginning the first day

of the month following the date the division certifies that a positive production response

has occurred and if the application for certification of positive production response is

filed:

(1)

not later than five years from the date the division issues the certification

of approval of the enhanced recovery project or expansion if the enhanced recovery

project or expansion is designated a secondary recovery project; or

(2)

not later than seven years from the date the division issues the

certification of approval of the enhanced recovery project or expansion if the enhanced

recovery project or expansion is designated a tertiary recovery project.

J. Qualification for the recovered oil tax rate ends on the first day of the first

calendar month that begins on or after the ninety-first day following the termination of

the enhanced recovery project or expansion.

K. If the active operation of an approved enhanced recovery project or expansion is

terminated, the operator shall notify the division and the secretary of taxation and

revenue in writing, not later than the thirtieth day after the termination of the enhanced

recovery project or expansion.

L. In addition to the powers enumerated in Section 70-2-12 NMSA 1978, the

division shall adopt, promulgate and enforce rules and regulations concerning the

approval of the applications, the designation of the affected areas and the operation,

expansion and termination of the enhanced recovery projects as provided for in the

Enhanced Oil Recovery Act.

Cite this section

N.M. Stat. § 7-29A-3

https://lawconsensus.com/codes/new-mexico/chapter-7/7-29a-3/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.