N.M. Stat. § 69-36-11
Existing mining operations; closeout plan required
Text of § 69-36-11
A. An owner or operator of an existing mining operation shall submit a permit
application to the director by December 31, 1994. The permit application shall contain
all information required by regulation of the commission, including a proposed
compliance schedule for submission of a closeout plan within the shortest time
practicable. The director shall approve or deny the permit application within six months
after it has been deemed complete.
B. The owner or operator of an existing mining operation shall submit a closeout
plan in accordance with the compliance schedule in the permit. The compliance
schedule in the permit shall require submission of a closeout plan by December 31,
1995 unless the operator shows good cause for a further extension of time. The director
shall approve a modification of a permit for an existing mining operation incorporating a
closeout plan or portion of a closeout plan if:
(1)
the closeout plan and permit application is complete;
(2)
the closeout plan permit fee has been paid and the financial assurance is
adequate and has been provided;
(3)
the closeout plan specifies incremental work to be done within specific
time frames that, if followed, will reclaim the physical environment of the permit area to
a condition that allows for the reestablishment of a self-sustaining ecosystem on the
permit area following closure, appropriate for the life zone of the surrounding areas
unless conflicting with the approved post-mining land use; provided that for purposes of
this section, upon a showing that achieving a post-mining land use or self-sustaining
ecosystem is not technically or economically feasible or is environmentally unsound, the
director may waive the requirement to achieve a self-sustaining ecosystem or post-
mining land use for an open pit or waste unit if measures will be taken to ensure that the
open pit or waste unit will meet all applicable federal and state laws, regulations and
standards for air, surfacewater and ground water protection following closure and will
not pose a current or future hazard to public health or safety; and
(4)
the secretary of environment has provided a written determination in the
form prescribed in Paragraph (2) of Subsection P of Section 7 [69-36-7 NMSA 1978] of
the New Mexico Mining Act.
C. An approval granted pursuant to this section may be revoked or suspended by
order of the director for violation of a provision of the approved closeout plan or permit
for the existing mining operation, an approval condition, a regulation of the commission
or a provision of the New Mexico Mining Act.