A. No later than eight months from the date on which the Surface Mining Act is
approved as part of a state program within the meaning of Section 503 of the federal
Surface Mining Control and Reclamation Act of 1977, 30 U.S.C. Section 1253 (1977),
no person shall engage in or carry out any surface coal mining operations unless such
person has first obtained a permit issued by the director pursuant to Section 14 [69-
25A-14 NMSA 1978] of the Surface Mining Act; provided, that a person conducting
surface coal mining operations under a permit issued pursuant to Laws 1972, Chapter
68, as amended in effect upon the effective date of the Surface Mining Act or issued
prior to the approval of a state program may conduct such operations beyond such
period if an application for a permit has been filed in accordance with the provisions of
that act, and the initial administrative decision has not been rendered.
B. All permits issued pursuant to the requirements of the Surface Mining Act shall
be issued for a term not to exceed five years; provided, that if the applicant
demonstrates that a specified longer term is reasonably needed to allow the applicant to
obtain necessary financing for equipment and the opening of the operation and if the
application is full and complete for such specified longer term, the director may grant a
permit for the longer term. A successor in interest to a permittee who applies for a new
permit within thirty days of succeeding to such interest and who is able to obtain the
bond coverage of the original permittee may continue surface coal mining and
reclamation operations according to the approved mining and reclamation plan of the
original permittee until the successor's application is granted or denied.
C. A permit shall terminate if the permittee has not commenced the surface coal
mining operations covered by such permit within three years of the issuance of the
permit; provided, that the director may grant reasonable extensions of time upon a
showing that such extensions are necessary by reason of litigation precluding such
commencement or threatening substantial economic loss to the permittee, or by reason
of conditions beyond the control and without the fault or negligence of the permittee.
Provided further, that with respect to coal to be mined for use in a synthetic fuel facility
or specific major electric generating facility, the permittee shall be deemed to have
commenced surface coal mining operations at such time as the construction of the
synthetic fuel or generating facility is initiated.
D. Any valid permit issued pursuant to the Surface Mining Act shall carry with it the
right of successive renewal upon expiration with respect to areas within the boundaries
of the existing permit. The permittee may apply for renewal and the renewal shall be
issued (provided that on application for renewal the burden shall be on the opponents of
renewal), subsequent to fulfillment of the public notice requirements of Sections 17 and
18 [69-25A-17 and 69-25A-18 NMSA 1978] of that act unless it is established that and
[any] written findings by the director are made that:
(1)
the terms and conditions of the existing permit are not being satisfactorily
met;
(2)
the present surface coal mining and reclamation operation is not in
compliance with the environmental protection standards of the Surface Mining Act or
regulations promulgated thereunder;
(3)
the renewal requested substantially jeopardizes the operator's continuing
responsibility on existing permit areas;
(4)
the operator has not provided evidence that the performance bond in
effect for the operation will continue in full force and effect for any renewal requested in
the application as well as any additional bond the director might require pursuant to
Section 13 [69-25A-13 NMSA 1978] of the Surface Mining Act; or
(5)
any additional revised or updated information required by the director has
not been provided. Prior to the approval of any renewal of permit, the director shall
provide notice to the appropriate public authorities.
E. If an application for renewal of a valid permit includes a proposal to extend the
mining operation beyond the boundaries authorized in the existing permit, the portion of
the application for renewal of a valid permit which addresses any new land areas shall
be subject to the full standards applicable to new applications under the Surface Mining
Act. Provided, that if the surface coal mining operations authorized by a permit issued
pursuant to that act were not subject to the standards contained in Subparagraphs (a)
and (b) of Paragraph (5) of Subsection B of Section 14 [69-25A-14 NMSA 1978] of that
act by reason of complying with the proviso of Paragraph (5) of Subsection B of Section
14 [69-25A-14 NMSA 1978] of that act, then the portion of the application for renewal of
the permit which addresses any new land areas previously identified in the reclamation
plan submitted pursuant to Section 12 [69-25A-12 NMSA 1978] of that act shall not be
subject to the standards contained in such subparagraphs.
F. Any permit renewal shall be for a term not to exceed the period of the original
permit established by the Surface Mining Act. Application for permit renewal shall be
made at least one hundred twenty days prior to the expiration of the valid permit.