Release of performance bonds

N.M. Stat. § 69-25A-23 · Last amended 1979 · Text from the 2026.09.1 snapshot

Text of § 69-25A-23

A. The permittee may file a request with the director for the release of all or part of a

performance bond or deposit. Within thirty days after any application for bond or deposit

release has been filed with the director, the operator shall submit a copy of an

advertisement placed at least once a week for four successive weeks in a newspaper of

general circulation in the locality of the surface coal mining operation. Such

advertisement shall be considered part of any bond release application and shall

contain a notification of the precise location of the land affected, the number of acres,

the permit and the date approved, the amount of the bond filed and the portion sought

to be released, and the type and appropriate dates of reclamation work performed, and

a description of the results achieved as they relate to the operator's approved

reclamation plan. In addition, as part of any bond release application, the applicant shall

submit copies of letters which he has sent to adjoining property owners, local

governmental bodies, planning agencies and sewage and water treatment authorities or

water companies in the locality in which the surface coal mining and reclamation

activities took place, notifying them of his intention to seek release from the bond.

B. Upon receipt of the notification and request, the director shall within thirty days

conduct an inspection an evaluation of the reclamation work involved. Such evaluation

shall consider, among other things, the degree of difficulty to complete any remaining

reclamation, whether pollution of surface and subsurface water is occurring, the

probability of continuance or future occurrence of such pollution and the estimated cost

of abating such pollution. The director shall notify the permittee in writing of his decision

to release or not to release all or part of the performance bond or deposit within sixty

days from the filing of the request, if no public hearing is held pursuant to Subsection F

of this section, and if there has been a public hearing held pursuant thereto, within thirty

days thereafter.

C. The director may release in whole or in part the bond or deposit if he is satisfied

the reclamation covered by the bond or deposit or portion thereof has been

accomplished as required by the Surface Mining Act according to the following

schedule:

(1)

when the operator completes the backfilling, regrading and drainage

control of a bonded area in accordance with his approved reclamation plan, the release

of sixty percent of the bond or collateral for the applicable permit area;

(2)

after revegetation has been established on the regraded mined lands in

accordance with the approved reclamation plan. When determining the amount of bond

to be released after successful revegetation has been established, the director shall

retain that amount of the bond for the revegetated area which would be sufficient for a

third party to cover the cost of reestablishing revegetation and for the period specified

for operator responsibility in Section 19 [69-25A-19 NMSA 1978] of the Surface Mining

Act for reestablishing revegetation. No part of the bond or deposit shall be released

under this paragraph so long as the lands to which the release would be applicable are

contributing suspended solids to streamflow or runoff outside the permit area in excess

of the requirements set by Section 19 of that act or until soil productivity for prime

farmlands has returned to equivalent levels of yield as non-minded land of the same soil

type in the surrounding area under equivalent management practices as determined

from the soil survey performed pursuant to Section 10 [69-25A-10 NMSA 1978] of that

act. Where a silt dam is to be retained as a permanent impoundment pursuant to

Section 19 of that act, the portion of bond which relates to reclamation of the silt dam

may be released under this section so long as provisions for sound future maintenance

by the operator or the landowner have been made with the director;

(3)

when the operator has completed successfully all surface coal mining and

reclamation activities, the release of the remaining portion of the bond, but not before

the expiration of the period specified for operator responsibility in Section 19 of the

Surface Mining Act. Provided, that no bond shall be fully released until all reclamation

requirements of that act are fully met.

D. If the director disapproves the application for release of the bond or portion

thereof, the director shall notify the permittee, in writing, stating the reasons for

disapproval and recommending corrective actions necessary to secure the release and

allowing opportunity for a public hearing.

E. When any application for total or partial bond release is filed with the director, the

director shall notify the municipality, if any, in which the surface coal mining operation is

located by certified mail at least thirty days prior to the release of all or a portion of the

bond.

F. Any person with a valid legal interest which might be adversely affected by

release of the bond or the responsible officer or head of any federal, state and local

governmental agency which has jurisdiction by law or special expertise with respect to

any environmental, social or economic impact involved in the operation, or is authorized

to develop and enforce environmental standards with respect to such operations shall

have the right to file written objections to the proposed release from bond to the director

within thirty days after the last publication of the notice pursuant to Subsection A of this

section. If written objections are filed and a hearing is requested, the director shall

inform all the interested parties of the time and place of the hearing, and hold a public

hearing in the locality of the surface coal mining operation proposed for bond release

within thirty days of the request for such hearing. The date, time and location of such

public hearing shall be advertised by the director in a newspaper of general circulation

in the locality for two consecutive weeks, and shall hold a public hearing in the locality of

the surface coal mining operation proposed for bond release or at Santa Fe at the

option of the objector, within thirty days of the request for such hearing.

G. Without prejudice to the rights of the objectors, the applicant or the

responsibilities of the director pursuant to this section, the director may establish an

informal conference as provided in Section 17 [69-25A-17 NMSA 1978] of the Surface

Mining Act to resolve such written objections.

H. For the purpose of such hearing, the director shall have the authority and is

hereby empowered to administer oaths, subpoena witnesses or written or printed

materials, compel the attendance of witnesses or production of the materials and take

evidence including but not limited to inspections of the land affected and other surface

coal mining operations carried on by the applicant in the general vicinity. A verbatim

record of each public hearing required by the Surface Mining Act shall be made, and a

transcript made available on the motion of any party or by order of the director.