N.M. Stat. § 67-3-8.4

Department; powers

N.M. Stat. § 67-3-8.4 · Last amended 2022 · Text from the 2026.09.1 snapshot

Text of § 67-3-8.4

A. The secretary may use an alternative to the design-bid-build project delivery

method for project procurement to allow the department to use the services of a

construction manager general contractor. No more than twenty-five percent of the

projects placed on the department's letting schedule in any calendar year may be let

pursuant to the design and build project delivery method pursuant to Section 13-1-119.2

NMSA 1978 or the construction manager general contractor delivery method pursuant

to the Transportation Construction Manager General Contractor Act [13-1-122.1 to 13-1-

122.4 NMSA 1978].

B. As used in this section, "letting schedule" means the department's construction

projects that are posted to give notice to the public prior to receiving bids on any project.