Partial payments on road contracts; progress estimates
Text of § 67-3-48
limitation; division of amounts.
Partial payments may be made on any contract for highway improvement under the
provisions of this act, as the work progresses. Progress estimates shall be based on
materials in place and labor expended thereon, but no more than ninety-five percent of
the contract price of the work shall be paid in advance of the full completion of such
contract and its acceptance by the state highway engineer. The state and county shall
each pay its proportionate share of such partial payments on the certification of the
amount thereof by the state highway engineer.