LawCensus
New Mexico Statutes

N.M. Stat. § 63-9-6

Issuance of certificate; territory on map

N.M. Stat. § 63-9-6 · Last amended 1965 · Text from the 2026.09.1 snapshot

Text of § 63-9-6

A. After conclusion of a hearing on an application for a certificate of convenience

and necessity the commission shall make and file an order containing its findings of fact

and decision. The order shall become operative twenty days after issuance, except as

the commission may otherwise provide.

B. The commission shall grant all certificates as required by Section 4 [63-9-4

NMSA 1978] of this act.

C. As to all applications other than those based upon Section 4 of this act, the

commission has the power, after having determined public convenience and necessity,

to grant a certificate as applied for, or to refuse to grant it, or to grant it for the

construction or operation of only a portion of the contemplated plant or system or

extension thereof, or for the partial exercise only of the rights and privilege sought, and

may attach to the exercise of the rights and privilege granted by a certificate such terms

and conditions as in its judgment the public convenience and necessity may require.

D. The geographical field or area that a telephone company is authorized and

required to serve by a certificate shall be defined on a map which will be part of the

certificate. The commission shall prescribe the form of the map to be used.

Cite this section

N.M. Stat. § 63-9-6

https://lawconsensus.com/codes/new-mexico/chapter-63/63-9-6/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.