N.M. Stat. § 62-9-3
Location control; limitations
Text of § 62-9-3
A. The legislature finds that it is in the public interest to consider any adverse effect
upon the environment and upon the quality of life of the people of the state that may
occur due to plants, facilities and transmission lines needed to supply present and
future electrical services. It is recognized that such plants, facilities and transmission
lines will be needed to meet growing demands for electric services and cannot be built
without in some way affecting the physical environment where these plants, facilities
and transmission lines are located. The legislature therefore declares that it is the
purpose of this section to provide for the supervision and control by the commission of
the location within this state of new plants, facilities and transmission lines for the
generation and transmission of electricity for sale to the public.
B. A person, including any municipality, shall not begin the construction of any plant
designed for or capable of operation at a capacity of three hundred thousand kilowatts
or more for the generation of electricity for sale to the public within or without this state,
whether or not owned or operated by a person that is a public utility subject to regulation
by the commission, or of transmission lines in connection with such a plant, on a
location within this state unless the location has been approved by the commission. For
the purposes of this section, "transmission line" means any electric transmission line
and associated facilities designed for or capable of operations at a nominal voltage of
two hundred thirty kilovolts or more, to be constructed in connection with and to transmit
electricity from a new plant for which approval is required.
C. Application for approval shall contain all information required by the commission
to make its determination, be made in writing setting forth the facts involved and be filed
with the commission. The commission shall, after a public hearing and upon notice as
the commission may prescribe, act upon the application. The commission may condition
its approval upon a demonstration by the applicant that it has received all necessary air
and water quality permits. A public utility regulated by the commission may submit an
application pursuant to Section 62-9-1 NMSA 1978 for a certificate of public
convenience and necessity prior to filing an application for location approval pursuant to
this section in order to determine the need for the generating plant or transmission line
prior to determination of the appropriate location.
D. Approval shall not be required for additions to or modifications of an existing
plant or transmission line.
E. The commission shall approve the application for the location of the generating
plant unless the commission finds that the operations of the facilities for which approval
is sought will not be in compliance with all applicable air and water pollution control
standards and regulations existing or will unduly impair system reliability. The
commission shall not require compliance with performance standards other than those
established by the agency of this state having jurisdiction over a particular pollution
source.
F. The commission shall approve the application for the location of the transmission
lines unless the commission finds that the location will unduly impair important
environmental values or the operation of the proposed transmission lines will unduly
impair power system reliability.
G. An application shall not be approved pursuant to this section that violates an
existing state, county or municipal land use statutory or administrative regulation unless
the commission finds that the regulation is unreasonably restrictive and compliance with
the regulation is not in the interest of the public convenience and necessity, in which
event and to the extent found by the commission, the regulation shall be inapplicable
and void as to the siting. When it becomes apparent to the commission that an issue
exists with respect to whether a regulation is unreasonably restrictive and compliance
with the regulation is not in the interest of public convenience and necessity, it shall
promptly serve notice of that fact by certified mail upon the agency, board or
commission having jurisdiction for land use of the area affected and shall make the
agency, board or commission a party to the proceedings upon its request and shall give
it an opportunity to respond to the issue. The judgment of the commission shall be
conclusive on all questions of siting, land use, aesthetics and any other state or local
requirements affecting the siting.
H. A public utility subject to the jurisdiction of the commission may elect to file an
application pursuant to this section with the commission for location approval of an
electric transmission line or associated facilities designed for or capable of operation at
a nominal voltage of one hundred fifteen kilovolts or more but less than two hundred
thirty kilovolts if:
(1)
the public utility files an application for construction, extension, rebuilding
or improvement of the electric transmission line or associated equipment under any
applicable county or municipal land use statute, ordinance or administrative regulation;
and
(2)
the agency, board or commission of the county or municipality
disapproves the application. For purposes of this subsection, "disapprove" means the
failure of the county or municipal agency, board or commission to issue a final order
approving the application within two hundred forty days of the public utility's filing of a
complete application with the agency, board or commission. An application shall be
deemed complete if within fifteen working days of the public utility's filing of the
application, or a supplement or amendment thereto, the agency, board or commission
fails to send written notice to the public utility enumerating the specific requirements
under the applicable county or municipal land use statute, ordinance or administrative
regulation that the application fails to satisfy.
I. Upon consideration of the application and the standards set forth in Subsection G
of this section, the commission may authorize construction, extension, rebuilding or
improvement of the transmission line or facilities notwithstanding the prior disapproval of
the county or municipal agency, board or commission. The judgment of the commission
shall be conclusive on all questions of siting, land use, aesthetics and any other state or
local requirements affecting the siting.
J. Nothing in this section shall be deemed to confer upon the commission power or
jurisdiction to regulate or supervise any person, including a municipality, that is not
otherwise a public utility regulated and supervised by the commission, with respect to its
rates and service and with respect to its securities, nor shall any other provision of the
Public Utility Act be applicable with respect to such a person, including a municipality.
K. The commission may approve an application filed pursuant to this section without
a formal hearing if no protest is filed within sixty days of the date that notice is given that
the application has been filed. The commission shall issue its order granting or denying
the application within six months from the date the application is filed with the
commission; provided, however, that:
(1)
if a public utility simultaneously files an application for approval of location
of a transmission line pursuant to this section and an application for a certificate of
public convenience and necessity pursuant to Subsection B of Section 62-9-1 NMSA
1978, the commission shall issue its order granting or denying the applications within
nine months from the date the applications are filed with the commission; provided,
however, that the commission may extend the time for granting approval an additional
six months for good cause shown;
(2)
if a public utility files an application for approval of location of a
transmission line pursuant to this section after its application for a certificate of public
convenience and necessity has been approved pursuant to Subsection B of Section 62-
9-1 NMSA 1978, the commission shall issue its order granting or denying the
application for approval of location of a transmission line within ninety days from the
date the application is filed with the commission; and
(3)
if a public utility files an application for approval of location of a
transmission line pursuant to this section while its application for a certificate of public
convenience and necessity is pending pursuant to Subsection B of Section 62-9-1
NMSA 1978, and the application for a certificate is subsequently approved, the
commission shall issue its order granting or denying the application for approval of
location of a transmission line within ninety days from the date the application for
certificate of public convenience and necessity is approved.
L. Failure to issue its order approving or denying an application filed pursuant to this
section within the time periods set forth in Subsection [J] K of this section is deemed to
be approval of the application; provided, however, that the commission may extend the
time for granting approval for a transmission line that is subject to this section for an
additional nine months upon finding that the additional time is necessary to determine if
the proposed location of the line will unduly impair important environmental values.
M. In determining if the proposed location of the transmission line will unduly impair
important environmental values, the commission may consider the following factors:
(1)
existing plans of the state, local government and private entities for other
developments at or in the vicinity of the proposed location;
(2)
fish, wildlife and plant life;
(3)
noise emission levels and interference with communication signals;
(4)
the proposed availability of the location to the public for recreational
purposes, consistent with safety considerations and regulations;
(5)
existing scenic areas, historic, cultural or religious sites and structures or
archaeological sites at or in the vicinity of the proposed location; and
(6)
additional factors that require consideration under applicable federal and
state laws pertaining to the location.