A. No public utility shall begin the construction or operation of any public utility plant

or system or of any extension of any plant or system without first obtaining from the

commission a certificate that public convenience and necessity require or will require

such construction or operation. This section does not require a public utility to secure a

certificate for an extension within any municipality or district within which it lawfully

commenced operations before June 13, 1941 or for an extension within or to territory

already served by it, necessary in the ordinary course of its business, or for an

extension into territory contiguous to that already occupied by it and that is not receiving

similar service from another utility. If any public utility or mutual domestic water

consumer association in constructing or extending its line, plant or system unreasonably

interferes or is about to unreasonably interfere with the service or system of any other

public utility or mutual domestic water consumer association rendering the same type of

service, the commission, on complaint of the public utility or mutual domestic water

consumer association claiming to be injuriously affected, may, upon and pursuant to the

applicable procedure provided in Chapter 62, Article 10 NMSA 1978, and after giving

due regard to public convenience and necessity, including reasonable service

agreements between the utilities, make an order and prescribe just and reasonable

terms and conditions in harmony with the Public Utility Act [Articles 1 through 6 and 8

through 13 of Chapter 62 NMSA 1978] to provide for the construction, development and

extension, without unnecessary duplication and economic waste.

B. If a certificate of public convenience and necessity is required pursuant to this

section for the construction or extension of a generating plant or transmission lines and

associated facilities, a public utility may include in the application for the certificate a

request that the commission determine the ratemaking principles and treatment that will

be applicable for the facilities that are the subject of the application for the certificate. If

such a request is made, the commission shall, in the order granting the certificate, set

forth the ratemaking principles and treatment that will be applicable to the public utility's

stake in the certified facilities in all ratemaking proceedings on and after such time as

the facilities are placed in service. The commission shall use the ratemaking principles

and treatment specified in the order in all proceedings in which the cost of the public

utility's stake in the certified facilities is considered. If the commission later decertifies

the facilities, the commission shall apply the ratemaking principles and treatment

specified in the original certification order to the costs associated with the facilities that

were incurred by the public utility prior to decertification.

C. The commission may approve the application for the certificate without a formal

hearing if no protest is filed within sixty days of the date that notice is given, pursuant to

commission order, that the application has been filed. The commission shall issue its

order granting or denying the application within nine months from the date the

application is filed with the commission. Failure to issue its order within nine months is

deemed to be approval and final disposition of the application; provided, however, that

the commission may extend the time for granting approval for an additional six months

for good cause shown.

D. Notwithstanding the time lines contained in Subsection C of this section, for

applications certified by the economic development department pursuant to Subsection

F of Section 62-6-26 NMSA 1978, the commission shall issue an order granting or

denying the application within six months from the date the application is filed with the

commission. Failure to issue the commission's order within six months is deemed to be

approval and final disposition of the application; provided, however, that the commission

may extend the time for granting approval for an additional three months for good cause

shown.

E. In an application for a certificate of public convenience and necessity for an

energy storage system, the commission shall approve energy storage systems that:

(1)

reduce costs to ratepayers by avoiding or deferring the need for

investment in new generation and for upgrades to systems for the transmission and

distribution of energy;

(2)

reduce the use of fossil fuels for meeting demand during peak load

periods and for providing ancillary services;

(3)

assist with ensuring grid reliability, including transmission and distribution

system stability, while integrating sources of renewable energy into the grid;

(4)

support diversification of energy resources and enhance grid security;

(5)

reduce greenhouse gases and other air pollutants resulting from power

generation;

(6)

provide the public utility with the discretion, subject to applicable laws and

rules, to operate, maintain and control energy storage systems so as to ensure reliable

and efficient service to customers; and

(7)

are the most cost effective among feasible alternatives.

F. As used in this section:

(1)

"energy storage system" means methods and technologies used to store

electricity; and

(2)

"mutual domestic water consumer association" means an association

created and organized pursuant to the provisions of:

(a) Laws 1947, Chapter 206; Laws 1949, Chapter 79; or Laws 1951, Chapter

52; or

(b) the Sanitary Projects Act [Chapter 3, Article 29 NMSA 1978].

Cite this section

N.M. Stat. § 62-9-1

https://lawconsensus.com/codes/new-mexico/chapter-62/62-9-1/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.