Payments; prompt pay required; withholding prohibited

N.M. Stat. § 57-28-5 · Last amended 2007 · Text from the 2026.09.1 snapshot

Text of § 57-28-5

A. Except as provided in Subsection B of this section, all construction contracts

shall provide that payment for amounts due shall be paid within twenty-one days after

the owner receives an undisputed request for payment. Payment by the owner to the

contractor may be made by first-class mailing, electronic funds transfer or by hand

delivery of the undisputed amount of a pay request based on work completed or service

provided under the contact. If the owner fails to pay the contractor within twenty-one

days after receipt of an undisputed request for payment, the owner shall pay interest to

the contractor beginning on the twenty-second day after payment was due, computed at

one and one-half percent of the undisputed amount per month or fraction of a month

until the payment is issued. If an owner receives an improperly completed invoice, the

owner shall notify the sender of the invoice within seven days of receipt in what way the

invoice is improperly completed, and the owner has no further duty to pay on the

improperly completed invoice until it is resubmitted as complete.

B. A local public body may make payment within forty-five days after submission of

an undisputed request for payment when grant money is a source of funding, if:

(1)

the construction contract specifically provides in a clear and conspicuous

manner for a payment later than twenty-one days after submission of an undisputed

request for payment; and

(2)

the following legend or substantially similar language setting forth the

specified number of days appears in clear and conspicuous type on each page of the

plans, including bid plans and construction plans:

"Notice of Extended Payment Provision

This contract allows the owner to make payment within ____________ days after

submission of an undisputed request for payment.".

C. All construction contracts shall provide that contractors and subcontractors make

prompt payment to their subcontractors and suppliers for amounts owed for work

performed on the construction project within seven days after receipt of payment from

the owner, contractor or subcontractor. If the contractor or subcontractor fails to pay the

contractor's or subcontractor's subcontractor and suppliers by first-class mail or hand

delivery within seven days of receipt of payment, the contractor or subcontractor shall

pay interest to the subcontractors and suppliers beginning on the eighth day after

payment was due, computed at one and one-half percent of the undisputed amount per

month or fraction of a month until payment is issued. These payment provisions apply to

all tiers of contractors, subcontractors and suppliers.

D. A creditor shall not collect, enforce a security interest against, garnish or levy

execution on those progress payments or other payments that are owed by an owner,

contractor or subcontractor to a person, or the owner's contractor's or subcontractor's

surety, who has furnished labor or material pursuant to a construction contract.

E. When making payments, an owner, contractor or subcontractor shall not retain,

withhold, hold back or in any other manner not pay amounts owed for work performed.