N.M. Stat. § 48-3-25
Enforcement of lien
Text of § 48-3-25
Three (3) months after the debt for which the lien is claimed becomes due, the lien
claimant may enforce such lien by either a suit to foreclose the lien or by a sale as
hereinafter provided.