LawCensus
New Mexico Statutes

N.M. Stat. § 48-2A-5

Stop notices; contents

N.M. Stat. § 48-2A-5 · Last amended 1989 · Text from the 2026.09.1 snapshot

Text of § 48-2A-5

A stop notice shall not be effective unless:

A. it is signed and verified by the claimant or his agent, accompanied with a bond as

provided for in Section 7 [48-2A-7 NMSA 1978] of the Stop Notice Act, is served

pursuant to Section 6 [48-2A-6 NMSA 1978] of the Stop Notice Act and states in

general terms all of the following:

(1)

the name of the claimant;

(2)

the date the claimant files the preliminary notice;

(3)

the date the claimant presented his request for payment to the original

contractors;

(4)

the name of the owner and original contractor of the residential site;

(5)

a description of the kind of labor or materials furnished, or agreed to be

furnished, for the residential site;

(6)

the name of the person who ordered the labor or who accepted the

materials;

(7)

the total cost of all the labor or materials to be furnished to the residential

site;

(8)

the cost of the labor furnished or materials already furnished;

(9)

the balance of the money due; and

(10)

a demand that the construction lender, if any, or the owner, if there is no

construction lender, withhold a sufficient amount of money from the construction loan

funds to satisfy the demand of the claimant;

B. a preliminary notice was given by the claimant, in accordance with Section 6 of

the Stop Notice Act, within twenty days after the claimant first began to furnish work or

materials to the residential site;

C. if the claimant does not deliver the preliminary notice within twenty days after the

claimant first began to furnish work or material to the site improvement, he may still

deliver a preliminary notice but he shall lose his stop notice rights for all work performed

or materials furnished more than twenty days before the preliminary notice actually is

given; and

D. it is delivered, pursuant to Section 6 of the Stop Notice Act, no earlier than twenty

days or later than thirty days from the date the subcontractor or materialman presented

his request for payment to the original contractor.