LawCensus
New Mexico Statutes

N.M. Stat. § 48-2-2.1

Procedure for perfecting certain mechanics' and

N.M. Stat. § 48-2-2.1 · Last amended 2007 · Text from the 2026.09.1 snapshot

Text of § 48-2-2.1

materialmen's liens.

A. The provisions of Subsections B through D of this section do not apply to claims

of liens made on residential property containing four or fewer dwelling units, to claims of

liens made by an original contractor or to claims of liens made by mechanics or

materialmen who contract directly with the original contractor. For purposes of this

section, "original contractor" means a contractor that contracts directly with the owner.

B. No lien of a mechanic or a materialman claimed in an amount of more than five

thousand dollars ($5,000) may be enforced by action or otherwise unless the lien

claimant has given notice in writing of the claimant's right to claim a lien in the event of

nonpayment and that notice was given not more than sixty days after initially furnishing

work or materials, or both, by either certified mail, return receipt requested, facsimile

with acknowledgement or personal delivery to:

(1)

the owner or reputed owner of the property upon which the improvements

are being constructed; or

(2)

the original contractor, if any.

C. If the owner or the original contractor claims lack of notice as a defense to the

enforcement of a lien described in Subsection B of this section, the owner or contractor

shall show that upon the request of the mechanic or materialman that the owner or

contractor furnished to the lien claimant not more than five days after such request was

made:

(1)

the original contractor's name, address and license number, if there is an

original contractor on the project;

(2)

the owner's name and address;

(3)

a description of the property or a description sufficiently specific for actual

identification of the property; and

(4)

the name and address of any bonding company or other surety that is

providing either a payment or performance bond for the project.

D. The notice required to be given by the claimant pursuant to the provisions of

Subsection B of this section shall contain:

(1)

a description of the property or a description sufficiently specific for actual

identification of the property;

(2)

the name, address and phone number, if any, of the claimant; and

(3)

the name and address of the person with whom the claimant contracted or

to whom the claimant furnished labor or materials, or both.

E. A person required by the provisions of Subsection B of this section to give notice

to enforce the person's claim of lien may elect not to give the notice, but may give the

required notice at a later time. If the person elects to do so, the lien shall apply only to

the work performed or materials furnished on or after the date thirty days prior to the

date the notice was given. The provisions of Subsections C and D of this section apply

to any notice given under this subsection.