N.M. Stat. § 48-2-2.1
Procedure for perfecting certain mechanics' and
Text of § 48-2-2.1
materialmen's liens.
A. The provisions of Subsections B through D of this section do not apply to claims
of liens made on residential property containing four or fewer dwelling units, to claims of
liens made by an original contractor or to claims of liens made by mechanics or
materialmen who contract directly with the original contractor. For purposes of this
section, "original contractor" means a contractor that contracts directly with the owner.
B. No lien of a mechanic or a materialman claimed in an amount of more than five
thousand dollars ($5,000) may be enforced by action or otherwise unless the lien
claimant has given notice in writing of the claimant's right to claim a lien in the event of
nonpayment and that notice was given not more than sixty days after initially furnishing
work or materials, or both, by either certified mail, return receipt requested, facsimile
with acknowledgement or personal delivery to:
(1)
the owner or reputed owner of the property upon which the improvements
are being constructed; or
(2)
the original contractor, if any.
C. If the owner or the original contractor claims lack of notice as a defense to the
enforcement of a lien described in Subsection B of this section, the owner or contractor
shall show that upon the request of the mechanic or materialman that the owner or
contractor furnished to the lien claimant not more than five days after such request was
made:
(1)
the original contractor's name, address and license number, if there is an
original contractor on the project;
(2)
the owner's name and address;
(3)
a description of the property or a description sufficiently specific for actual
identification of the property; and
(4)
the name and address of any bonding company or other surety that is
providing either a payment or performance bond for the project.
D. The notice required to be given by the claimant pursuant to the provisions of
Subsection B of this section shall contain:
(1)
a description of the property or a description sufficiently specific for actual
identification of the property;
(2)
the name, address and phone number, if any, of the claimant; and
(3)
the name and address of the person with whom the claimant contracted or
to whom the claimant furnished labor or materials, or both.
E. A person required by the provisions of Subsection B of this section to give notice
to enforce the person's claim of lien may elect not to give the notice, but may give the
required notice at a later time. If the person elects to do so, the lien shall apply only to
the work performed or materials furnished on or after the date thirty days prior to the
date the notice was given. The provisions of Subsections C and D of this section apply
to any notice given under this subsection.
Cite this section