N.M. Stat. § 47-6-22
Time limit on administrative action
Text of § 47-6-22
A. All opinions required of public agencies or submitted by an Indian nation, tribe or
pueblo shall be furnished to the board of county commissioners within thirty days after
the public agencies or Indian nation, tribe or pueblo receives the written request and
accompanying information from the board of county commissioners. If the board of
county commissioners does not receive a requested opinion within the thirty-day period,
the board shall proceed in accordance with its own best judgment concerning the
subject of the opinion request. The failure of a public agency or Indian nation, tribe or
pueblo to provide an opinion when requested by the board of county commissioners
does not indicate that the subdivider's provisions concerning the subject of the opinion
request were acceptable or unacceptable or adequate or inadequate.
B. Final plats submitted to the board of county commissioners for approval shall be
approved or disapproved at a public meeting of the board of county commissioners
within thirty days of the date the final plat is deemed complete.
C. If the board of county commissioners does not act upon a final plat within the
required period of time, the subdivider shall give the board of county commissioners
written notice of its failure to act. If the board of county commissioners fails to approve
or reject the final plat within thirty days, the board of county commissioners shall, upon
demand by the subdivider, issue a certificate stating that the final plat has been
approved.