LawCensus
New Mexico Statutes

N.M. Stat. § 47-6-22

Time limit on administrative action

N.M. Stat. § 47-6-22 · Last amended 2009 · Text from the 2026.09.1 snapshot

Text of § 47-6-22

A. All opinions required of public agencies or submitted by an Indian nation, tribe or

pueblo shall be furnished to the board of county commissioners within thirty days after

the public agencies or Indian nation, tribe or pueblo receives the written request and

accompanying information from the board of county commissioners. If the board of

county commissioners does not receive a requested opinion within the thirty-day period,

the board shall proceed in accordance with its own best judgment concerning the

subject of the opinion request. The failure of a public agency or Indian nation, tribe or

pueblo to provide an opinion when requested by the board of county commissioners

does not indicate that the subdivider's provisions concerning the subject of the opinion

request were acceptable or unacceptable or adequate or inadequate.

B. Final plats submitted to the board of county commissioners for approval shall be

approved or disapproved at a public meeting of the board of county commissioners

within thirty days of the date the final plat is deemed complete.

C. If the board of county commissioners does not act upon a final plat within the

required period of time, the subdivider shall give the board of county commissioners

written notice of its failure to act. If the board of county commissioners fails to approve

or reject the final plat within thirty days, the board of county commissioners shall, upon

demand by the subdivider, issue a certificate stating that the final plat has been

approved.

Cite this section

N.M. Stat. § 47-6-22

https://lawconsensus.com/codes/new-mexico/chapter-47/47-6-22/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.