N.M. Stat. § 3-59-9
Use of proceeds from sale of bonds
Text of § 3-59-9
The proceeds from the sale of any bonds issued under authority of the Pollution
Control Revenue Bond Act shall be applied only for the purpose for which the bonds
were issued; provided, that any accrued interest and premiums received in any such
sale shall be applied to the payment of the principal of or the interest on the bonds sold;
and provided further, that if for any reason any portion of such proceeds shall not be
needed for the purpose for which the bonds were issued, then such balance of the
proceeds shall be applied to the payment of the principal of or the redemption premium,
if any, and interest on the bonds, and provided further, that any portion of the proceeds
from the sale of the bonds, including refunding bonds, or any accrued interest and
premium, received in any such sale, may, in the event the money currently will not be
needed or cannot be effectively used to the advantage of the municipality for the
purposes herein provided, be invested, in accordance with the procedures and subject
to any restrictions established by the ordinance and other proceedings under which the
bonds are issued, in any securities without limitation except as expressly provided to the
contrary in Section 3-59-8 NMSA 1978, if such investment will not interfere with the use
of such funds for the primary purposes as herein provided. The cost of acquiring any
project or projects shall be deemed to include the following:
A. the actual cost of the construction of any part of a project or projects which shall
be constructed, including architects', attorneys' and engineers' fees;
B. the purchase price of any part of a project or projects that may be acquired by
purchase;
C. the actual cost of the extension of any utility to the project site or sites, all
expenses in connection with the authorization, sale and issuance of the bonds to
finance such acquisition; and
D. the interest on any bonds issued by the same municipality for the same or any
other project or projects for a reasonable time prior to construction, during construction
and for not exceeding six months after completion of construction.
Cite this section
N.M. Stat. § 3-59-9
https://lawconsensus.com/codes/new-mexico/chapter-3/3-59-9/
LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.