[Architect, employment by commissioner; contract for

N.M. Stat. § 19-12-4 · Last amended 1959 · Text from the 2026.09.1 snapshot

Text of § 19-12-4

construction of building; notice of letting; rejection of bids;

performance bond.]

The commissioner is empowered to employ an architect after competition among

three or more architects of the state, on the basis of the best design submitted, and to

contract for the construction of a building with the lowest and best bidder among three

or more bidders, after notice in two consecutive issues of any Santa Fe or Albuquerque,

New Mexico, newspaper not less than twenty days before the day of letting. The

commissioner may either let the work in one entire contract or to different contractors,

as the commissioner may deem advisable. The commissioner may reject any or all bids

and call for new bids. The commissioner may require a performance bond with surety in

an amount he deems necessary from bidders.