LawCensus
New Mexico Statutes

N.M. Stat. § 13-4-36

Substitution of subcontractor

N.M. Stat. § 13-4-36 · Last amended 2005 · Text from the 2026.09.1 snapshot

Text of § 13-4-36

A. No contractor whose bid is accepted shall substitute any person as subcontractor

in place of the subcontractor listed in the original bid, except that the using agency shall

consent to the substitution of another person as a subcontractor in the following

circumstances:

(1)

when the subcontractor listed in the bid, after having had a reasonable

opportunity to do so, fails or refuses to execute a written contract, when such written

contract, based upon the general terms, conditions, plans and specifications for the

project involved and the terms of such subcontractor's written bid, is presented to him

by the contractor;

(2)

when the subcontractor listed in the original bid becomes bankrupt or

insolvent prior to execution of a subcontract;

(3)

when the using agency refuses to approve the subcontractor listed in the

original bid, provided such approval has been reserved in the bidding documents;

(4)

when the subcontractor listed in the original bid fails or refuses to perform

his subcontract;

(5)

when the contractor demonstrates to the using agency or its duly

authorized officer that the name of the subcontractor was listed as the result of an

inadvertent clerical error;

(6)

when a bid alternate accepted by the using agency causes the listed

subcontractor's bid not to be low;

(7)

when the contractor can substantiate to the using agency that a listed

subcontractor's bid is incomplete;

(8)

when the listed subcontractor fails or refuses to meet the bond

requirements of the contractor;

(9)

when it is determined that the listed subcontractor does not have a proper

license to perform the work and the contractor has submitted the name of the

subcontractor along with proof that the subcontractor bid work for which he was not

licensed by the construction industries division of the regulation and licensing

department; or

(10)

when it is determined by the using agency, the prime contractor or the

director of the labor and industrial division of the labor department that a listed

subcontractor is not a registered subcontractor on the date bids are unconditionally

accepted for consideration.

B. Prior to approval of the contractor's request for substitution of a subcontractor,

the using agency shall give notice in writing to the listed subcontractor of the

contractor's request to substitute and of the reasons for the request. The notice shall be

served by certified or registered mail to the last known address of the subcontractor.

The listed subcontractor who has been so notified has five working days within which to

submit written objections to the substitution to the using agency. Failure to file written

objections shall constitute the listed subcontractor's consent to the substitution. If written

objections are filed, the using agency shall give at least five working days notice in

writing to the listed subcontractor of a hearing by the using agency on the contractor's

request for substitution.

C. No contractor whose bid is accepted shall permit any subcontract to be

voluntarily assigned or transferred or allow it to be performed by anyone other than the

original subcontractor listed in the original bid without the consent of the using agency.

D. No contractor whose bid is accepted, other than in the performance of change

orders causing changes or deviations from the original contract, shall sublet or

subcontract any portion of the work in excess of the listing threshold as to which his

original bid did not designate a subcontractor unless:

(1)

the contractor fails to receive a bid for a category of work. Under such

circumstances, the contractor may subcontract. The contractor shall designate on the

listing form that no bid was received; or

(2)

the contractor fails to receive more than one bid for a category of work.

Under such circumstances, the contractor may subcontract. The contractor shall state

on the listing form that only one subcontractor's bid was received, together with the

name of the subcontractor. This designation shall not occur more than one time on the

subcontractor list.

Cite this section

N.M. Stat. § 13-4-36

https://lawconsensus.com/codes/new-mexico/chapter-13/13-4-36/

LawCensus reproduces the text of the law for reference. It may not show the most recent changes. Check the official source before you rely on it: official text. This is general information, not legal advice.