N.M. Stat. § 13-4-20
Additional bond in case of insolvency of sureties
Text of § 13-4-20
Whenever in its judgment any surety on such bond shall be insolvent, or for any
cause is not a proper or sufficient surety, the obligee may require the contractor to
furnish a new or additional bond or security within ten days; and thereupon, if the
obligee shall so order, all work on said contract shall cease until such new or additional
bond or security shall be furnished. If not furnished within said time, the obligee may at
its option take over and complete said work as the agent and at the expense of the
contractor and sureties, either doing the work on force account or letting the same by
contract, and shall be entitled to use any equipment, materials and supplies of the
delinquent contractor in completing said work.